Energy Policy
  Vital Statistics
  Power Finance Corporation-Kerala
  Energy Management Centre - Kerala
  Kerala State Electricity Board
  ... Profile 
  ... Generation 
  ... Transmission 
  ... Distribution 
  ... Tariff 
  ... Reforms 
... Who is who 
  Anert
  Organisational Structure
List and Address of Area Wise Officers
Details of Works/Programs / Schemes / Services
 
   
 
 
 


Kerala State Electricity Board


Transmission


         The Kerala power system consists of 17 hydel stations including 2 captive power plants 2 thermal stations, 3 IPPs, 5 major inter-state transmission lines, one 400 KV sub-section, and II Nos. 220 KV substations with the interconnecting grid. The main grid is in 220 KV system. The energy requirement for the year is estimated to be 13,000mu. Out of this about 6,200mu is expected from hydel sources, 3,500mu from central generating stations, 2,500mu from the IPPs and the balance from the remaining sources. The present peak load demand is about 2300MW and is expected to increase up to 2,500 MW during March/April next year. We have a storage capacity of 3843mu and the present storage is about 72% of the full capacity.

Load Dispatch Centre

       The Load Dispatch Station is situated at Kalamassery. Real-time data from the generating stations and sub-stations are obtained in the Load Dispatch Station through Power Line Carrier Communication Network (PLCC). Depending on the load condition, generators in various power stations are synchronized and loaded to meet the varying load requirements. Shift-engineers in the control room of load dispatch station regulate the power generation as well as import as per the real-time demand. This is carried out with the aid of computerized Supervisory Control and Data Acquisition System (SCADA). The state LD is connected to the Southern Regional Load Dispatch Centre at Bangalore. The central share and drawal is regulated by the SRLDC at Bangalore, Water availability, inflow, consumption, demand etc. are daily collected and monitored in the Load Dispatch Station. Generation schedule for the day and long term planning of generation is carried out based on these details collected in the LD center. Deputy Chief Engineer in-charge of Load Dispatch Station Co-ordinates all these activities. All details for the monthly Load Generation Generation Balance (LGB), operation co-ordination with SREB, inter-state energy transactions, etc. are handled by this wing.

       The Unified Load Dispatch and Communication Scheme is implemented in the state also as part of the National Policy for Unified Load Dispatching, and the formation of a National Grid and a National Load Dispatch Station. The implementation works for the entire Southern Region is coordinated by PGCIL., KSEB is providing the infrastructure facilities for the implementation of the scheme. The works are nearing completion and the new LD set up in Kerala is expected to become operational during this financial year itself.

        As per the scheme three sub load dispatch centers will become operational at Thiruvananthapuram, Kalamassery and Kannur in addition to the State LD Station at Kalamassery. Data from 30 important stations (RTU) are being collected for real time load dispatch activities. These stations include all major generating stations, all 220kV substations and major 110KV stations.

        The Load Dispatch Station is supported technically by the communication wing and protection wing. The communication wing is responsible for the upkeep of all communication networks, the SCADA system and the associated software for Energy Management. The Protection Wing, more popularly known the Relay Wing, is responsible for ensuring selectivity and sensitivity to fault clearance in the grid to achieve stability of the power system.

Communication System

        For ensuring effective and secured communication, KSEB is maintaining its own communication network. Earlier, the communication was predominantly through PLCC. Now, a microwave link is established from Thiruvananthapuram to Kalamassery and an optical fibre link is established from Kalamassery to Kannur. There are 10 nodal stations in this broadband communication network and the remote stations are hooked on to this network through PLCC. The broadband network is connected to the Regional LD Centre, Bangalore through the FO link from Madakathara through the 400KV interstate lines. The final integration works are in progress now. The microwave part is done by Alstom, optical fibre part by Pirelli and the SCADA and EMS are supplied by GE - Harris.

        At present, the Sub LD Stations are proposed to be manned in two shifts. The State LD Station will be manned in all the three shifts. With the commissioning of the ULDC Scheme, the Load Dispatch Activities in the State level, regional level and in the National level can be better coordinated resulting in better stability of the Grid

Plans for future

       Modernisation of the Load Dispatch is a continuing program so as to cater to the additions in the generation as well as to manage the power system to meet the demand for power. The typical additional works include acquisition of data from the new generating stations or grid stations as and when they are commissioned, acquisition of energy meter readings and real time control of the general at major power stations when the availability based tariff structure (ABT) is implemented etc.

        With the expansion of the power system, the traffic in the communication network increases, and it is necessary to replace the PLCC network with media supporting more bandwidth. A broadband communication network is already established from Kannur to Thiruvananthapuram. Additional broadband network is required in the grid to connect major stations lying away from this network. This additional network is being planned in such a way that the computerization and networking of all the offices of KSEB is also facilitated. The work is proposed in the 10th Five Year Plan. The spare capacity in the broadband network can be utilized to provide the communication infrastructure for commercial telecom operation. Discussions are also being held with the ER& DC, Thiruvananthapuram for providing communication facility for the networking the various offices of the Govt. of Kerala on a commercial basis.

         This not only has enough capacity to meet all our requirements of internal communication now carried out through PLCC, but also provides ample spare capacity to lease out to private telecom operators,. We have already signed an MOU with PGCL who has got licence as a National Telecom Operator for a joint venture to lease out the spare capacity in the wide-band for a nation wide telecom operation. This wide-band has also enough capacity to meet our future requirements such as video conferencing, wide-area networking for the computers installed in KSEB (Intra Net), facility for Internet Services (ISP) etc.

Transmission system over the decades

Transmission Lines (Circuit Kms

1960

1970

1980

1990

2000

2001

400KV

0

0

0

0

0

0

220KV

0

317

854

981

2056

2216

110KV

527

1350

1545

2297

2870

2990

66KV

1373

1711

2005

2482

2674

2490

No.of EHT Sub Stations

22

59

86

130

178

182

Step Down Transformer Capacity MVA

201

1219

2832

4174

9363

9921

Plans for the future
  no. of stations

 

Short Term Plan (20001-2002)

Mid Term Plan(2002-2003)

Long Term Plan (2003-2007

220KV

5

7

5

110 KV

42

48

32

66 KV

8

8

-

33 KV

29

98

-

Total

84

161

37


For more details visit
www.kseboard.com

 

 





Designed & Maintained by: C-DIT, Thiruvananthapuram, www.cdit.org
for Public Relations Department, Govt. of Kerala.