1. Whom do you approach to get water released
through the Canal System of Irrigation Projects?
All
the completed Irrigation Projects have an Operation and
Maintenance Division which is headed by an Executive Engineer.
The Executive Engineer in charge of the Operation and
Maintenance Division may be contacted to get water released
through the Canal system.
2.
Is there any system for warning people before release of
water through Dams/Canal system?
Yes,
the Executive Engineer in charge of the Dam/Head Works
will issue necessary warnings through Press/Media etc,
well in advance about the opening of Dam shutters/Canal
systems, warning the Public to take care, and not to allow
people/cattle graze in river beds etc.
3.
Who is to be informed in the case of a breach of a river
or Costal erosion in beaches?
The
Executive Engineer of Water Resource (Major Irrigation)
Division is the officer to take immediate action in the
case of a breach of a river or Costal erosion in beaches
under his jurisdiction.
The
district wise jurisdiction and the office address are
as follows:
| Thiruvananthapuram
District
(Whole
of Tvpm District) |
Executive
Engineer, Water Resource (Major Irrigation) Division,
Near Science & Technology Museum, PMG Junction,
Tvpm. Phone: 0471-2303189 |
| Kollam
& Pathanamthitta Districts
(Whole
of Kollam District and Pathanamthitta District and
up to Thotapally Spillway in NH-47 in Alappuzha District
|
Executive
Engineer, Water Resource (Major Irrigation) Division,
Asramam, Kollam. Phone: 0474-2746114 |
| Alappuzha
District (From Thotapally Spillway in NH-47 to border
of Ernakulam District) |
Executive
Engineer, Water Resource (Major Irrigation) Division,
Alappuzha Phone: 0477-2245312 |
| Kottayam
& Idukki District (Whole of Kottayam & Idukki
District) |
Executive
Engineer, Water Resource (Major Irrigation) Division,
Kottayam. Phone:0481-2584694 |
| Ernakulam
District (Whole of Ernakulam District) |
Executive
Engineer, Water Resource (Major Irrigation) Division,
Ernakulam. Phone: 0484-2422230 |
| Thrissur
District (Whole of Thrissur District) |
Executive
Engineer, Water Resource (Major Irrigation) Additional
Division, Chembukavu, Thrissur. Phone: 0487-2337339 |
| Malappuram
District (Whole of Malappuram District) |
Executive
Engineer, Water Resource (Major Irrigation) Division,
Malappuram. Phone: 0483-2766186 |
| Palakkad
District (Whole of Palakkad District) |
Executive
Engineer, Water Resource (Major Irrigation) Division,
Palakkad. Phone: 0491-2522808 |
| Kozhikode
District & Wayanad District (Whole of Kozhikode
& Wayanad District) |
Executive
Engineer, Water Resource (Major Irrigation) Division,
Civil Station, Kozhikode. Phone: 0495-2370751 |
| Kannur
District (Whole of Kannur District) |
Executive
Engineer, Water Resource (Major Irrigation) Division,
Tellicherry. Phone: 0490-2322148. |
| Kasargode
District (Whole of Kasargode District) |
Executive
Engineer, Water Resource (Major Irrigation) Division,
Kasargode. |
4. Who is to be contacted for matters regarding
Neyyar Irrigation Project Dam & Canal systems?
The
Executive Engineer of Water Resources (Major Irrigation)
Division, PMG Junction, Tvpm is the officer incharge of
Head Works and canals under Neyyar Irrigation Project.
5.
Who is responsible for the maintenance of Ulloor
Thodu/Amaiyamchan Thodu / Parvathi Puthan Aar / Pazhavangadi
canal system in Thiruvananthapuram city?
The
Executive Engineer of Water Resources (Major Irrigation)
Division, PMG Junction, Tvpm is the officer in charge
of the above canal system in Tvpm city.
6.
Who is responsible for the maintenance of Pattom
Thodu/Kochar Thodu / Aranoor Thodu canal system in Thiruvananthapuram
city?
The
Executive Engineer of Water Resources (Major Irrigation)
Division, Jalavignana Bhavan, Ambalamukku, Kowdiar, Tvpm
is the officer in charge of the above canal system in
Tvpm city.
7.
Who is coordinating the Departments Inter-State Water Affairs?
A
cell is constituted for the Department Inter-State Water
Affairs including that of Cauvery and the cell is functioning
at the 3rd floor of Vikas Bhavan, Thiruvananthapuram
and at New Delhi, with Er.T.K.Sasi, Chief Engineer (Irrigation
and Administration) as the Convenor.
8.
Which office is doing the Design of Structures required
for the Department/Design of Buildings/Investigation of
New Irrigation Projects/Research & Documentation work
in the Department?
Aboard
viz. Irrigation Design and Research Board (IDRB) with
a Chief Engineer as head is doing the required Designs,
Investigation, Research etc work of the Department.
9.
What is the total sanctioned Manpower of the Department
in various categories?
-
Chief
Engineer 6 nos.
-
Superintending
Engineers-25 nos.
-
Executive
Engineers-955 nos.
-
Asst.
Executive Engineers 362 nos.
-
Asst.
Engineers-955 nos.
-
1st
Grade Draftsman-884 nos.
-
Scientific
Asst. 3 nos.
-
Foreman
1 no.
-
Plumbing
Inspector-3 nos.
-
Senior
Mechanic 6 nos.
-
Heavy
machine Operator-2 nos.
-
Mechanic
9 nos.
-
Line
man Grade I 5 nos.
-
Canal
Inspector-2 nos.
-
Pump
Operator 26 nos.
-
Turner
8 nos.
-
Lab
Assistant 3nos.
-
Driver
cum operator-6 nos.
-
Light
Machine operator-2 nos.
-
Line
man Gr.II 2 nos.
-
Asst.
Pump operator-20 nos.
-
Operator
Mechanic 2nos
-
Black
Smith 23 nos.
-
Moulder
6 nos.
-
Welder
10 nos.
-
Mechanic
fitter 62 nos.
-
Pump
Cleaner 3nos.
-
Oil
Engine Driver-6 nos.
-
Loco
Operator 1nos.
-
Assistant
Surgeon- 2nos.
-
Pharmacist
1 nos.
-
Nursing
Assistant 1 no.
-
Carpenter
3 nos.
-
Wireman
2 nos.
-
Drilling
Plant Operator- 4 nos.
-
Bull
dozer operator 1 no.
-
Excavator
operator- 1 no.
-
Plumber
1 no.
-
Mixer
Driver 3 nos.
-
Computer
Operator 1no.
-
2nd
Grade Draftsman-887 nos.
-
3rd
Grade Draftsman 1539 nos.
-
Blue
printers 62 nos.
-
Research
Assistant 20 nos.
-
Finance
Officer 4 nos.
-
Administrative
Officer 1 no.
-
Law
Officer 2 nos.
-
Administrative
Assistant 15 nos.
-
Financial
Assistant 10 nos.
-
Senior
Superintendent 28 nos.
-
Divisional
Accountant 62 nos.
-
Junior
Superintendent- 165 nos.
-
Head
Clerks 219 nos.
-
Confidential
Assistant 30 nos.
-
Fair
copy Supdt. 8 nos.
-
Typist
544 nos.
-
Information
Asst. 1 no.
-
Sergeant
2 nos.
-
Dredger
Driver-6 nos.
-
-
Canal
Officer 7 nos.
-
Boat
Reg: Officer 2nos.
-
Jetty
Supdt: -45 nos.
-
Boat
Syrang 4nos.
-
Motor
Boat Syrang 1no.
-
Roller/Larry
Driver 9 nos.
-
Butler
2 nos.
-
cook/Watchman-4
nos.
-
Gardener
5 nos.
-
Telephone
Operator 1no.
-
IB
watchman 2 nos.
-
Helper
10 nos.
-
Roller
Driver 26 nos.
-
Record
Attender 12 nos.
-
Attender
16 nos.
-
Boat
Driver 5 nos.
-
Boat
Cleaner 2 nos.
-
AN
Midwife 1 no.
-
Hospital
Attender 1no.
-
Mason
3 nos.
-
Scavenger
1 no.
-
Painter
1 no.
-
Caretaker
1 no.
-
Spray
Painter 1 no.
-
Light
Keeper 14 nos.
-
LD/UD
Clerks 1872 nos.
-
Part
time Sweepers 148 nos.
-
Driver
263 nos.
-
LD
Compiler 7 nos.
-
UD
Compilers 7 nos.
-
Peons
857 nos.
-
Lascar/Watcher
1056 nos.
-
Typist
Clerk 2 nos.
-
Full
Time Sweeper 7 nos.
The
Total of each Category include those Posts deployed
to Local Self Government Department.
10.
What is the difference between a Minor Irrigation
Scheme, Medium Irrigation scheme and Major Irrigation
scheme?
Minor
Irrigation schemes are those benefiting on Irrigable
command area of not more than 15 hectares.
Medium
Irrigation Schemes are those with a cultivable area
of 15 hectares or more, and not more than 10,000 hectares,
including Lift Irrigation schemes.
Those
schemes above 10,000 hectares are Major Irrigation schemes.
Those
classifications are as per revised Kerala Irrigation
and Water Conservation Act 2003, dated 18th
September 2003.
11.
Which Agency is the main provider of Loan Assistance to
the Department?
National
bank of Agriculture and Rural Development (NABARD) is
providing loan assistance for Minor Irrigation works
under Rural Infrastructure Development Fund (RIDF) through
Phases I to IX, since 1995.
12.
What is the Outlay for Minor Irrigation in the 10th
Plan?
Rs.155.00
Crores is the 10th Plan Outlay for Minor
Irrigation.